Work Nearly Complete At Bauer Drain

The work areas that have been occupied by heavy construction equipment over the past 18 months are starting to green up with new vegetation as the Bauer Drain and Sycamore Creek Mitigation Project draws to a close. Contractors are working on finishing touches on-site including grass growth and other minor adjustments and corrections as the newly relocated Drain flows under Grimes Road and around the tank storage facilities. The Hayhoe Riverwalk in the City of Mason has residents and wildlife alike enjoying the improvements along the Sycamore Creek.

Minor work items will be completed within the next month before final completion status is reached. If you have any questions or concerns with the conditions of the work site, please contact Terry Belill, inspector, 989-996-5228.

Major Construction Wraps-up at Bauer Drain

Over the past month, the contractor has worked to complete the last major work items on the drain and prepare the site to be seeded so that vegetation may be restored to disturbed areas. This work included the restoration of laydown areas and hauling routes, installation of trash racks on pipe ends, and placing concrete for the final junction chamber cap.

Over the next several weeks, regular inspections will be made to monitor the grass growth and correct any deficiencies noted. Additional work will be needed at each junction chamber to install access hatches and other items, which will take place over the next few months.

If you have any questions or concerns with the conditions of the work site, please contact Terry Belill, inspector, 989-996-5228.

CONTRACTOR WORKING ON FINAL RESTORATION

Our contractor has made progress over the past several weeks to bring our project closer to being restored. Specific items completed include the completion of the 24-inch storm sewer branch, fence reconstruction, topsoil application, and final grading in various locations. Our contractor will continue their efforts to bring all portions of the project to final grade, and apply topsoil, seed, and polymer to establish vegetation growth.

If you have any questions or concerns, please contact Terry Belill, inspector, 989-996-5228

Progress on the Bauer Drain

Since the conclusion of paving, the contractor has been working around the site to complete road shoulders, final grading, drain crossings, driveway repairs, and other unfinished items. Construction work on the project is nearing completion. All work is on track to be finished this summer.

If you have any questions or concerns, please contact Terry Belill, inspector, 989-996-5228.

Memorial Day 2022

There will be no work on Monday, May 30, 2022 in observance of Memorial Day. Let us celebrate, honor, and remember our fallen service members with gratitude and pride. 

GRIMES ROAD CLOSED FOR PAVING MAY 19, 2022

Paving on Grimes Road is scheduled to conclude today following the placement of the final top course of asphalt on the western (southbound) lane. Paving will begin around 12:30PM today, and Grimes Road will be closed to through traffic, traffic shall detour via Mt. Pleasant Road. The western (southbound) lane cannot be driven on while the asphalt cools. After the fresh asphalt has cooled the road will be opened to traffic, likely around 6:00PM or later, pending any delays with the placement of the asphalt and the forecasted warm weather conditions. The following properties will be inaccessible to vehicle traffic between 12:30PM and 6:00PM:

  1. 2716 Grimes Road-Davis
  2. 2700 Grimes Road-Gordon
  3. 2570 Grimes Road-Bauer
  4. 2340 Grimes Road-Guinan
  5. Farms and Vacant Properties west side of Grimes Road (Glenn, Bauer, and Tri-State)

There will be staff on-site throughout the day to assist with conflicts, coordination and assistance. If access or coordination is needed, please contact one of the following on-site contacts:

  1. Construction Inspector, Terry Belill (989) 996-5228
  2. Project Manager, Chris Mattson (989) 213-6365
  3. Drain Engineer, Angie Cosman (517) 719-5431
  4. Ingham County Deputy Drain Commissioner, Carla Clos (517) 719-4913

JACK AND BORE CROSSINGS COMPLETE

All jack and bore crossings of petroleum pipelines are now concluded, with the completion of the Enbridge and Vector bores just before the Thanksgiving holiday. Lowe Construction was on-site to perform the work. A 48″ diameter steel pipe was bored under the oil and gas utilities to provide for a trenchless crossing. Safety coordination and utility representative oversight was top priority as the work progressed. This crossing was completed safely and without incident.

Preparations for cast-in-place concrete structures began immediately following the completion of the bore. These and other drainage structures, as well as storm sewer installation will take place next to connect the bored steel pipe to the already installed portion of the relocated Bauer Drain. All this work is in an effort to conclude major work items along Grimes Road before the end of 2021, weather dependent.

If you have any questions or concerns, please contact Terry Belill, inspector, 989-996-5228.

SYCAMORE CREEK STREAM MEASURES INSTALLED

Jackson Dirt Works has completed the initial installation of stream enhancement measures along the Sycamore Creek. Following this milestone, a comprehensive inspection of the installed measures will take place to determine if any adjustments are needed to the project as a whole. Adjustments to stream measures and restoration activities along the Hayhoe Riverwalk will take place over the next few weeks. Expect to see intermittent use of the Riverwalk to make these minor adjustments and restore the pathway corridor. As always, personnel will be placed along the path to warn pedestrians of any construction activity.

Future work along the Riverwalk, as part of this project, may include but is not limited to; signage installation, asphalt path repairs, and other restoration activity along the Riverwalk.

The Sycamore Creek Enhancement Project is being constructed as mitigation for the Bauer Drain Relocation Project by a contractor retained by the Ingham County Drain Commissioner Patrick E Lindemann.  If you have any questions or concerns, please contact Terry Belill, inspector, 989-996-5228.