Bauer Drain Relocation and Sycamore Creek MITIGATION


The purpose of the Bauer Drain Relocation project is to relocate from a petroleum storage facility the open channel County Drain, considered a stream tributary to the Red Cedar River. The project is designed to protect the waters of the state from known and potential contamination and to assure the continued operation of the drainage service by the County Drain without risk for interruption due to the adjacent industrial uses.

Construction Status


BAUER DRAIN Grimes Road is CLOSED.
Week of October 18 | Storm sewer installation, cleanup and road base construction along Grimes Road, weather dependent. Dewatering and preparation for next jack and bore crossing.

Week of October 25 | Storm sewer installation, road construction, cleanup and restoration. Installation of next jack and bore crossing, weather dependent.


Updated: October 18, 2021

SYCAMORE CREEK Hayhoe Riverwalk is OPEN.
Week of October 18 | No work along the Hayhoe Riverwalk this week.

Week of October 25 | No work anticipated.