April 26, 2021 Cleanup work from maintenance tree clearing.

May 5, 2021 Start channel work east of Mt. Pleasant Road.

June 1, 2021 Mobilize equipment, stage materials, and install soil erosion and sedimentation control measures in preparation for pipe installation work.

June 21, 2021 Start drain relocation/pipe installation work.

July 3-5, 2021 NO WORK PERMITTED – INDEPENDENCE DAY HOLIDAY

July 6, 2021 Mobilization equipment and stage materials for Sycamore Creek mitigation in Mason, MI.

July 12, 2021 Start installation of Sycamore Creek mitigation in Mason, MI (RIVERWALK MAY BE INTERMITTENLY CLOSED).

July 19, 2021 Begin dewatering efforts for inverted siphon/junction chamber construction.

July 26, 2021 Start construction work within Grimes Road (ROAD TO BE CLOSED).

September 7, 2021 Start jack and bore crossings of petroleum pipelines.

October 15, 2021 Deadline to complete Sycamore Creek stream habitat improvements.

Early November 2021 Finish jack and bore crossings of petroleum pipelines.

December 22, 2021 Deadline to complete drain relocation.

January-March 2022 Fill and regrade existing channel through tank farm.

Spring/Summer 2022 Perform punchlist work, including paving Grimes Road.

Late July-Early October 2022 Ensure vegetation growth is acceptable with regular inspections. Install chamber accessories and plant trees at various locations.

November 15, 2022 Contract final completion date.