Work through the winter months has been dependent on weather conditions; however, a lot of progress has been made on-site with the Bauer Drain Relocation project. The primary work items include junction chamber construction and channel grading work adjacent to the petroleum storage properties.
Four junction chambers have been constructed on-site. The first two were constructed on the relocated Drain adjacent to the Enbridge and Vector pipelines to provide access for maintenance of the Drain under the pipelines. The third chamber was constructed along Grimes Road to act as an isolation point for stormwater runoff from Enbridge’s terminal facility. The last chamber was constructed west of Mt. Pleasant Road as an isolation point for stormwater from the Wolverine and Marathon properties. All chamber’s are currently secured using steel plates, as their lids are being manufactured off-site.
Work to fill and re-grade the existing channel, according to EGLE Permit No. WRP023342 v. 1, is currently underway for sections of the channel between Grimes Road and Mt Pleasant Road. This work also includes the removal, installation, and reconfiguration of several Drain crossings.
If you have any questions or concerns, please contact Terry Belill, inspector, 989-996-5228.