WORK WITHIN GRIMES ROAD PROGRESSING

Work is progressing satisfactorily to construct the relocated Bauer Drain within Grimes Road. Crews have been diligently installing the 48-inch diameter storm sewer, manhole structures, and the base material for the restored roadway. Grimes Road is still closed and will remain closed until the pipe installation is complete. A posted detour route via Mt. Pleasant Road is in place and can be found on our Project Maps page.

In addition to pipe installation, crews are also preparing for the trenchless crossings under critical petroleum pipelines. All of the petroleum pipelines are being positively identified ahead of time by means of hydro-excavation so that we may safely cross under the critical utilities. On-site personnel is working closely with pipeline safety representatives as the crossings work approaches.

If you have any questions or concerns, please contact Terry Belill, inspector, 989-996-5228.

BAUER DRAIN STORM SEWER PROGRESS

Construction crews began installing 48-inch round storm sewer this week after the completion of elliptical pipe installation. Restoration of previous work areas has been completed in an effort to reestablish vegetation. Progress will continue this week pending any delays from the rain in the forecast.

If you have any questions or concerns, please contact Terry Belill, inspector, 989-996-5228.